Commercial Permits

Freuesntly Asked Questions  

Work cannot start before a permit is issued.  We do offer Partial permits and Foundation only permits in order for the project to get started.  A foundation only permit would require two additional sets of plans to be submitted. A partial permit would require one additional set. A partial permit would be for underground plumbing and interior demolition. 

A Special Inspection as herein required of the materials, installation, fabrication, erection or placement of components and connections requiring special expertise to ensure compliance with approved construction documents and referenced standards. Examples of items that would require a Special Inspection but not limited to would be Field Welding, High Strength Bolting, High Strength Concrete, Epoxy Anchors.  ​

​​